[ARCHIVED] Highway 114 Construction Project

Hwy 114 Project

Stay up to date with the latest regarding the Highway 114 frontage road project that runs through Westlake and Southlake.  Throughout the duration of this project, various road closures and detours will be implemented which will affect drivers in the Trophy Club area. Thank you in advance for your patience. Hwy 114 Project 2When: Jan. 29, 2021 (Friday)

Where: Eastbound Dove Rd exit ramp

What:  Update pavement markings along Dove Rd exit ramp

Duration: One (1) day - daytime closure (9:00am to 3:00pm)

Impact(s):

  1. Closure of right lane (one (1) lane) of SH 114 eastbound main lanes from FM 1938 (Davis Blvd) to Dove Rd
  2. Closure of SH 114 eastbound Dove Rd exit ramp (west of Dove Rd)

 -----------------------------

When: Jan. 30, 2021 (Saturday)

Where: Dove Rd north of SH 114

What:  Construction zone setup, barrier installation

Duration: One (1) day – Barrier placement

            Ongoing – Construction zone

Impact(s):

  1. Closure of right lane (one (1) lane) of SH 114 westbound frontage road east of Dove Road
  2. Closure of right lane (one (1) lane) of Dove Road north of SH 114 frontage road 

------------------------------

When:        Feb. 6, 2021 (Saturday)

Where:       SH 114 eastbound entrance ramp at FM 1938 (Davis Blvd)
SH 114 eastbound main lanes (FM 1938 (Davis Blvd) to Kirkwood/Solana Blvd)

What:         Construction zone setup, barrier installation

Duration:  One (1) day – Barrier placement

Impact(s):

1.   Closure of SH 114 eastbound FM 1938 (Davis Blvd) entrance ramp (east of FM 1938 (Davis Blvd))

2.   Closure of right lane (one (1) lane) of SH 114 eastbound main lanes from FM 1938 (Davis Blvd) to Kirkwood/Solana Blvd

Hwy 114 Project

This will be a three-year TxDOT project including the following improvements to the highway frontage roads and ramp facilities from Westlake Parkway to Dove Road in Southlake.

Frontage Road Improvements (Green):

  • Eastbound frontage road – FM 1938 (Davis Blvd) to Kirkwood/Solana Blvd
  • Eastbound frontage road – Kirkwood/Solana Blvd to Dove Road
  • Westbound frontage road – Dove Road to Kirkwood/Solana Blvd

These improvements include extensions to the eastbound lanes of the frontage road from FM 1938 (Davis Blvd) to Dove Rd and the westbound lanes from Dove Rd to Kirkwood/Solana Blvd.

Impact: The U-Turn on the eastside of the FM 1938 (Davis Blvd) will be closed starting January 8. 

Barriers will be installed within the shoulder section along the mainlines of eastbound SH114 west of the FM 1938 (Davis Blvd) overpass beginning January 8th 

Ramp Improvements (orange):

  • Eastbound entrance ramps – Three (3) total

  • Eastbound exit ramps – Two (2) total
  • Westbound entrance ramps – Two (2) total
  • Westbound exit ramps – Two (2) total

These improvements include the realignment of the current ramps between FM 1938 (Davis Blvd) and Kirkwood/Solana Blvd.

Impact: Various ramps throughout the project limits will be closed at different times throughout the project. The first closure will occur with the entrance ramp west of FM 1938 (Davis Blvd)on January 8th.   

U-Turn Improvements(Blue):

  • Eastbound to westbound at Kirkwood/Solana Blvd

  • Westbound to eastbound at Kirkwood/Solana Blvd
  • Eastbound to westbound at Dove Road

These improvements include adding U-Turn under SH 114 and Kirkwood/Solana Blvd and Dove Road.

Impact: Various lane closures near the improvements will be closed at different times. The first U-turn improvements are anticipated to begin in the Spring of 2021. 


Thank you to our partners at the Town of Westlake for providing updates and details on this major project!

Facebook Twitter Email

Other News in TC News & Information

TC Team

TC Employee's ROCK!

Posted on: March 3, 2023
POWMIA Families

Calling all POW/MIA Families

Posted on: March 6, 2023
State of the Community (2)

TC State of the Community

Posted on: February 27, 2023
Pool

TC Community Pool Complex Gets A Makeover

Posted on: February 21, 2023
Special Election

May General Election Information

Posted on: January 18, 2023
Website Refresh (1)

Trophy Club Website Gets a Refresh

Posted on: February 14, 2023
Denise Deprato

Meet The Team - Denise Deprato

Posted on: January 25, 2023
Annual Report 2022

2022 Annual Report

Posted on: January 24, 2023
TC Alerts

Sign up for TC Alerts!

Posted on: June 24, 2022