Highway 114 Construction Project

Hwy 114 Project

Stay up to date with the latest regarding the Highway 114 frontage road project that runs through Westlake and Southlake.  Throughout the duration of this project, various road closures and detours will be implemented which will affect drivers in the Trophy Club area. Thank you in advance for your patience. 

February 03, 2021 Update:

Construction 2.3

When:        Feb. 6, 2021 (Saturday)

Where:       SH 114 eastbound entrance ramp at FM 1938 (Davis Blvd)

SH 114 eastbound main lanes (FM 1938 (Davis Blvd) to Kirkwood/Solana Blvd)

SH 114 eastbound exit ramp at Kirkwood/Solana Blvd

What:         Construction zone setup, barrier installation

Duration:  One (1) day – Barrier placement

Impact(s):

1.   Closure of SH 114 eastbound FM 1938 (Davis Blvd) entrance ramp (east of FM 1938 (Davis Blvd)) – Detour to be provided

2.   Closure of right lane (one (1) lane) of SH 114 eastbound main lanes from FM 1938 (Davis Blvd) to Kirkwood/Solana Blvd

3.   Closure of SH 114 eastbound Kirkwood/Solana Blvd exit ramp (west of Kirkwood/Solana Blvd) 

--------------

When:       Feb. 8, 2021 (Monday) – Feb. 12, 2021 (Friday)

                  Feb. 15, 2021 (Monday) – Feb. 19, 2021 (Friday)

Where:       SH 114 eastbound main lanes (FM 1938 (Davis Blvd) to Kirkwood/Solana Blvd)

What:         Retaining wall construction activities

Duration:  Two (2) weeks – Daytime closure (9:00am – 3:00pm)

Impact(s):

1.   Closure of right lane (one (1) lane) of SH 114 eastbound main lanes from FM 1938 (Davis Blvd) to Kirkwood/Solana Blvd


January 28, 2021 Update:

Hwy 114 Project 2

When: Jan. 29, 2021 (Friday)
Where: Eastbound Dove Rd exit ramp
What:  Update pavement markings along Dove Rd exit ramp
Duration: One (1) day - daytime closure (9:00am to 3:00pm)
Impact(s):

  1. Closure of right lane (one (1) lane) of SH 114 eastbound main lanes from FM 1938 (Davis Blvd) to Dove Rd
  2. Closure of SH 114 eastbound Dove Rd exit ramp (west of Dove Rd)

 -----------------------------

When: Jan. 30, 2021 (Saturday)
Where: Dove Rd north of SH 114
What:  Construction zone setup, barrier installation
Duration: One (1) day – Barrier placement
                     Ongoing – Construction zone
Impact(s):

  1. Closure of right lane (one (1) lane) of SH 114 westbound frontage road east of Dove Road
  2. Closure of right lane (one (1) lane) of Dove Road north of SH 114 frontage road 

------------------------------

When:        Feb. 6, 2021 (Saturday)
Where:       SH 114 eastbound entrance ramp at FM 1938 (Davis Blvd)
SH 114 eastbound main lanes (FM 1938 (Davis Blvd) to Kirkwood/Solana Blvd)
What:         Construction zone setup, barrier installation
Duration:  One (1) day – Barrier placement
Impact(s):

  1. Closure of SH 114 eastbound FM 1938 (Davis Blvd) entrance ramp (east of FM 1938 (Davis Blvd))
  2. Closure of right lane (one (1) lane) of SH 114 eastbound main lanes from FM 1938 (Davis Blvd) to Kirkwood/Solana Blvd

Hwy 114 Project

This will be a three-year TxDOT project including the following improvements to the highway frontage roads and ramp facilities from Westlake Parkway to Dove Road in Southlake.

Frontage Road Improvements (Green):

  • Eastbound frontage road – FM 1938 (Davis Blvd) to Kirkwood/Solana Blvd
  • Eastbound frontage road – Kirkwood/Solana Blvd to Dove Road
  • Westbound frontage road – Dove Road to Kirkwood/Solana Blvd

These improvements include extensions to the eastbound lanes of the frontage road from FM 1938 (Davis Blvd) to Dove Rd and the westbound lanes from Dove Rd to Kirkwood/Solana Blvd.

Impact: The U-Turn on the eastside of the FM 1938 (Davis Blvd) will be closed starting January 8. 

Barriers will be installed within the shoulder section along the mainlines of eastbound SH114 west of the FM 1938 (Davis Blvd) overpass beginning January 8th 

Ramp Improvements (orange):

  • Eastbound entrance ramps – Three (3) total

  • Eastbound exit ramps – Two (2) total
  • Westbound entrance ramps – Two (2) total
  • Westbound exit ramps – Two (2) total

These improvements include the realignment of the current ramps between FM 1938 (Davis Blvd) and Kirkwood/Solana Blvd.

Impact: Various ramps throughout the project limits will be closed at different times throughout the project. The first closure will occur with the entrance ramp west of FM 1938 (Davis Blvd)on January 8th.   

U-Turn Improvements(Blue):

  • Eastbound to westbound at Kirkwood/Solana Blvd

  • Westbound to eastbound at Kirkwood/Solana Blvd
  • Eastbound to westbound at Dove Road

These improvements include adding U-Turn under SH 114 and Kirkwood/Solana Blvd and Dove Road.

Impact: Various lane closures near the improvements will be closed at different times. The first U-turn improvements are anticipated to begin in the Spring of 2021. 

For more information, you can visit the Texas Department of Transportation Project Tracker here.
TxDot Map

Thank you to our partners at the Town of Westlake for providing updates and details on this major project! 

Facebook Twitter Email

Other News in TC News & Information

CORONAVIRUS (COVID-19) Vaccine Info

COVID-19 Vaccine Info

Posted on: December 30, 2020
Fun Run

Virtual Fun Run 4 Kindness

Posted on: February 1, 2021
Home Repair Fee Waived

Home Repair Permit Fee Temporarily Waived

Posted on: February 24, 2021
Trash Resumes

Trash Pick Up Resumes Tuesday 2/23

Posted on: February 17, 2021
TC Mud On Call Number

TC Water Update - Trophy Club Water SAFE!

Posted on: February 16, 2021
Power Outage

Oncor Power Outage News

Posted on: February 16, 2021
TC Alerts

Sign Up for TC Alerts

Posted on: February 16, 2021
Town Part of May ELection Canceled 2

No Opposition, No Council Election in May

Posted on: February 24, 2021
Street Panel Replacements

Street Panel Replacement

Posted on: January 4, 2021
TC Safest City 2

TC Named #2 Safest City in Texas

Posted on: December 18, 2020
Register Rover

Register Rover

Posted on: January 2, 2019
SM Branded News Take Me Home

Take Me Home Program Offered by TCPD

Posted on: July 13, 2020
Copy of Marquee - Text Only

COVID-19 TC Updates and Information

Posted on: January 28, 2020