Town Staff has diligently been working to ensure the successful installation of the parking lot near Bread Winners Cafe. Residents can expect around 80 spaces in this parking lot. The project is moving along as scheduled and will be completed on time!

Here is a quick snapshot of the project timeline:
January 17: Construction started
January 18-20: Materials arrive, grading and compacting begin
January 23-26: Grading and compacting finished, parking blocks installed
January 27: Parking lot is open!
Weather could alter the timeline