ABOUT the Trophy Club Town Center Project


Master developer Midtown Development, Inc, in conjunction with Beck Ventures, Inc, JSB Properties, LP, JLIS, LLC, Kriya Hotels, Green Brick Partners, and North American Properties are about to break ground on the Trophy Club Town Center, a 26 acre mixed-use development that will only enhance the Trophy Club community. Once completed, the Trophy Club Town Center will include 39 luxury townhomes, a 132 key Aloft Hotel, 60,000 square feet of retail space, 50,000 square feet of office space and 250 high-end apartments along with a manicured outdoor landscape, ample outdoor green space and patios, and other amenities. MORE>>

   

Project Updates


The Town staff intends to provide updates on the happenings as much as it is available.  Please remember that the information provided is what is available to staff via their team and other third parties and it is subject to change.  Staff will strive to keep Trophy Club looking and functioning at its best while keeping its residents informed to the best of their abilities.
 
6/22/2018 — 6:30 PM
PD-30, Trophy Club Town Center, is well underway as they continue with the storm drain and sanitary sewer installation. Crews are mobilizing daily to assist in completion of underground facilities

6/15/2018 — 3:30 PM
Current work is happening on grades and setting storm drain piping. Several hundred feet of fifty-four (54) inch pipes have been laid and bedded. Three (3) new utility crews are due in on Monday, June 18, 2018 and will advance the pace. Town staff is now making two (2) inspections a day to keep the project moving.

6/12/2018 — 8:00 AM

Work has begun and staff was able to fly a drone to capture aerial photos of the progress so far.  

     


5/30/2018 — 4:00 PM

Permits have been issued to representatives from North Texas Contracting for early site preparation, grading and tree removal on the Trophy Club Town Center (PD-30) site. During their visit, the contractor mentioned that crews and equipment are currently being mobilized to begin work.  The first noticeable activity on the site will be the installation of the required silt fencing for erosion control. During this process, the contractor will also establish the construction entrance for the project.
 
The contractor has assured staff that they will provide the Town with a preliminary schedule of work in the days to come. As more information is available, staff will communicate updates accordingly.

5/29/2018 — 9:00 AM
Updates Coming Soon 
 